|
|
 |
Pondage tests: principle, method
|
|
Pages in this section include:
This page provides a detailed description of the principle and method for
the pondage tests channel seepage identification and measurement
technique.
Principle
The pondage test method uses a water balance approach to determine
seepage losses in an isolated section of channel. Seepage losses
constitute the drop in water level over time in the pond (or volume
added to maintain a constant level) after accounting for evaporation,
rainfall and other inflows and outflows.
This method is a direct way of recording the losses through a section
of channel. As such it is considered to be a datum against which
other methods can be compared and calibrated.
Method
The pondage test method uses barriers or constructed pond banks to
form a pond within a section of channel. The location of the barriers
depends on project objectives, and might be determined by geophysical
surveys or perhaps anecdotal information.
Existing structures suitable for forming a sealed barrier can be
used to minimise the number of new barriers to be constructed.
A section of channel is blocked off with barriers at each end and
filled with water up to, or slightly higher than, the level at which
it usually flows during operation. As the water level in the channel
section falls, the level is measured by a staff, hook gauge, or a
water-level recorder. The time between measurements is also recorded,
necessary corrections for evaporation and rainfall made, and the
resulting seepage loss rate computed.
A variation of the normal pondage test involves adding water to maintain
a constant surface level. The volume of water added is measured and
is considered the seepage loss (allowing for evaporation and rainfall).
This method has the advantage of more accurately representing normal
flow conditions than the falling level test but depends on accurate
measurement of the pond depth.
The equation for calculating seepage losses using the pondage test
method is presented below (modified after Frevert and Ribbens (1988)
to allow for rainfall and evaporation). See also the graph below.

Units must be consistent for all terms in the equation.
If the only inflow into the reach is rainfall (which is often assumed
to be the case), the length of the reach drops out and the equation
reduces to:

Where (for above 2 equations):
These parameters are illustrated below:

Figure 1 – Channel cross section indicating
parameter values to calculate the seepage rate
| Data to be collected |
 |
Estimates of evaporation and rainfall can be obtained from the nearest
weather station. However, more accurate results can be achieved using
an evaporation pan and rainfall gauge adjacent to the pond.
As well as soil and hydraulic data for the channel, information about
silt layers lining the channel is important in interpretation of
results.
Site survey
The site should be surveyed before channel filling [while the channel
is empty] to collect information on channel bed levels, channel cross-sections
and structure or bank details. The survey should take account of
the following requirements.
- Full supply level (FSL) surveyed before pond construction works,
so that the pond can be filled to this level during the test.
- Reference pegs at each of the barriers, surveyed for location.
- Hook gauges surveyed at the 0 or 1.0m mark on the gauges, with
FSL and channel bed levels recorded at each gauge.
- Survey to define the channel cross-section as accurately as
possible at the pondage walls and approximately every 200m. The
recommended number of points to be collected in each cross-section
is presented in the table below. Each point in the cross-section
is to be surveyed for elevation and chainage. The minimum number
of points required also depends on the shape of the channel.
- If a pondage test is repeated at a site after a year or more,
the survey should be repeated in case there have been changes
to the channel cross-section due to channel operation and maintenance.
Recommended number of survey points to be included
in channel cross-section
| Survey
point |
Reference
|
LHS Natural Surface ( 5m
from toe of bank)
|
LNSO |
LHS Natural surface at toe of bank
|
LNS |
LHS Top of bank - outside
|
LTO |
LHS Top of bank - inside
|
LTI |
LHS Bed
|
LB |
Centre Bed
|
C |
RHS Bed
|
RB |
RHS Top of bank - inside
|
RTI |
RHS Top of bank - outside
|
RTO |
RHS Natural surface at toe of bank
|
RNS |
RHS Natural surface ( 5m
from toe of bank)
|
RNSO |
Survey definitions
Left-hand side (LHS) – Left-hand side based facing downstream
Right-hand side (RHS) – Right-hand side based facing downstream

Figure 2 –Survey points to be included
in channel cross-section
Elevations should be surveyed to Australian Height data (AHD). It
is beneficial to survey to Australian map grid (AMG) coordinates
to allow consistency with other spatial techniques such as geophysics
and groundwater bore locations for input to GIS mapping and analysis
systems. A site plan showing all survey channel data (preferably
an electronic version), should be prepared to help interpret pondage
test data and other related information.
Pondage test soil barrier construction


Figures 3 and 4 - Pond barrier showing
temporary plastic liner installation
| Pond set-up
and construction |
 |
Individual ponds can be tested for a site-specific investigation.
Multiple ponds may be used if data are required to extrapolate to
other parts of the channel in conjunction with other data such as
geophysical response for calibration. Barriers should be located
so that individual ponds coincide with sections showing similar geophysical
response. A minimum length of 50m is recommended. Back-to-back construction
minimises the number of barriers required to be constructed.
Using an excavator and plastic or rubber membrane liner, barriers
are compacted, lined and covered with soil to minimise or prevent
seepage. An excavator will be required for construction of the banks.
See figures 3 and 4 above showing two stages of a barrier under construction
in a full channel.
Landowner permission to use soil adjacent to temporary bank locations
saves on transportation. Holes are filled in when temporary barriers
are dismantled after the tests. Soil used for barriers should have
sufficient clay content.
| Installation
of monitoring gauges |
 |
Hook gauges
Hook gauges are to be installed at both ends of each pondage section
to eliminate potential wind effects. Gauges should be calibrated
to millimetre accuracy. Data loggers can produce more accurate results
and eliminate the need for gauge monitoring during the test.
Rainfall gauge and evaporation pan
Rainfall and evaporation must be measured to develop the water balance.
A rainfall gauge and class A evaporation pan should installed in
middle of the pond (or at the middle pondage for a series of ponds).
More accurate evaporation rates are obtained if the evaporation pan
is allowed to float in the pond. Specifications can be obtained from
the Bureau of Meteorology.
Filling methodology
Pondage tests within each section should start as close as possible
to simultaneously, with water levels at full supply level (FSL).
To account for losses during the initial wetting period of the soil,
the methodology should include one of the following:
- Filling the pondages above FSL and commencing the test when
the pondage level reaches the FSL.
- Maintaining the pondage levels at FSL for half to one day before
commencement of the test.
To obtain a consistent initial level across the ponds, barriers should
be constructed within one day, and a pump used to transfer water
from upstream into the ponds, and from pond to pond.
Set-up methods differ slightly vary depending on whether tests are
being conducted at the start or end of the irrigation season.
Filling methodology at end of channel operation
The furthest downstream bank should be constructed first, working
backwards towards the furthest upstream bank. The water level in
the most downstream pondage should be allowed to back up to the highest
degree, as this will experience the highest losses by the time the
final pondage is constructed. A pump might be required to top up
levels in the lower ponds before starting the test.
Filling methodology at beginning of channel operation
In dry conditions, the downstream bank can be fully constructed before
the release of the water. The remaining barriers can also be constructed,
taking advantage of the dry conditions.
To allow water to be transferred through the barriers, a suitably
sized pipe should be installed towards the top of each bank, and
each pipe adequately sealed when the filling of the ponds is completed.
The use of these pipes will enable equilibrium to be maintained across
all the ponds. A portable pump may be required to top up ponds.
Water being released to fill the ponds needs careful control. Once
the test has commenced the flow coming down the channel needs to
be virtually stopped. Overflow of the upstream bank cannot occur
during the test. This makes the timing of the test crucial and operations
personnel need to be prepared to shutdown the system for the test.
| Checking of site for all possible
inflows and outflows |
 |
During and after filling of the ponds, an inspection should be carried
out of all sealed structures and along both barriers of the test
reach, to check for leakage and other signs of water loss (e.g. stock
usage, pumps). If inflow or outflow sites are found, attempts should
be made to measure or eliminate them.
Pondage test operation
Duration of test
- The typical duration of a pondage test is in the range of four
to ten days.
- The duration of the test is best determined during the test
and is dependent on the amount of measured seepage. Results should
therefore be assessed daily during the test.
- If rainfall during the test causes significant uncontrolled
and unmeasured runoff into the pond, the test should be cancelled
or extended as this inflow will not be accounted for accurately
in the water balance.
Monitoring during the test
- Data measurements (water-level gauges, pan evaporation and
rainfall) should be taken daily, with at least two measurements
taken on the first day of the test.
- Accurate reading of hook gauges is usually only effective from
inside the channel, which may require wading into the channel.
- All water measurements should be recorded inside stilling wells
to minimise short-term variations in the water level (e.g. due
to wind-driven waves).
- Gauges at the upstream and downstream end of each pondage should
be read not more than 10 minutes apart.
- Data should be recorded on a spreadsheet similar to that shown
in Figure 2-5, which allows direct input for calculations.
| Evaluation of test results |
 |
The field-recorded data is used in the equations to determine the
estimated seepage rate. Download the Microsoft Excel spreadsheets
below for an example of, or to record your own pondage test calculation
output.
Related pages
|
 |
Pondage
tests: summary
Pondage tests: applicability,
practical implementation, experience from the trials, indicative
costs
|
|