IRRIGATION AUSTRALIA WEBSITE Channel Seepage Management Tool (Please click to return to home page)

About this website Contact us Site map

Home

Seepage risk, potential

Identification & measurement

General issues
Recom. approach &
techniques
Techniques

Inflow-outflow tests

Pondage tests

Point measurement

Soil & geological profile

Groundwater
assessment

Geophysical surveys

Remote sensing

Remediation

Remediation costs, benefits

Prioritisation of works

Project review

Case studies

Downloads

Glossary

References

Pondage tests: principle, method

On this page go to
Principle
Method
Data to be collected
Pond set-up and construction
Installation of monitoring gauges
Checking of site for all possible inflows and outflows
Pondage test operation
Evaluation of test results
Related pages

Pages in this section include:

 

Pondage tests; summary

Pondage tests: principle, method
  Pondage tests: applicability, practical implementation, experience from the trials, indicative costs

This page provides a detailed description of the principle and method for the pondage tests channel seepage identification and measurement technique.

Principle

The pondage test method uses a water balance approach to determine seepage losses in an isolated section of channel. Seepage losses constitute the drop in water level over time in the pond (or volume added to maintain a constant level) after accounting for evaporation, rainfall and other inflows and outflows.

This method is a direct way of recording the losses through a section of channel. As such it is considered to be a datum against which other methods can be compared and calibrated.

Method

The pondage test method uses barriers or constructed pond banks to form a pond within a section of channel. The location of the barriers depends on project objectives, and might be determined by geophysical surveys or perhaps anecdotal information.

Existing structures suitable for forming a sealed barrier can be used to minimise the number of new barriers to be constructed.

A section of channel is blocked off with barriers at each end and filled with water up to, or slightly higher than, the level at which it usually flows during operation. As the water level in the channel section falls, the level is measured by a staff, hook gauge, or a water-level recorder. The time between measurements is also recorded, necessary corrections for evaporation and rainfall made, and the resulting seepage loss rate computed.

A variation of the normal pondage test involves adding water to maintain a constant surface level. The volume of water added is measured and is considered the seepage loss (allowing for evaporation and rainfall). This method has the advantage of more accurately representing normal flow conditions than the falling level test but depends on accurate measurement of the pond depth.

The equation for calculating seepage losses using the pondage test method is presented below (modified after Frevert and Ribbens (1988) to allow for rainfall and evaporation). See also the graph below.

Equation for calculating seepage losses using the pondage test method

Units must be consistent for all terms in the equation.

If the only inflow into the reach is rainfall (which is often assumed to be the case), the length of the reach drops out and the equation reduces to:

Equation for calculating seepage losses using the pondage test method (alternate)

Where (for above 2 equations):

  Enter parameter values to calculate the seepage rate.

W = Average surface width between t1 and t2 [metres]

 

d1 = Water level at t1 (averaged between u/s and d/s gauges)[metres]

 

d2 = Water level at t2 (averaged between u/s and d/s gauges)[metres]

 

E = Evaporation along reach between t1 and t2 [metres] *

 

R = Rainfall along reach between t1 and t2 [metres]

 

P = Averaged wetted perimeter between t1 and t2 [metres]

 

I = Inflow along reach between t1 and t2 (e.g. rainfall, runoff)[m3/day]

 

L = Length of canal reach [metres]

 

t1 = Time at first measurement of water levels [time]

   

t2 = Time at subsequent measurement of water levels [time]

   

t2-t1 = Elapsed time in hours (Automatically converts to days)

 

Annual days of operation(optional)**

S = Seepage rate [volume/area/time]

m/day (m3/m2/day)

 

mm/day

 

ML/km/year

Note:
*Calculation of evaporation from the pond (E) is estimated from the pan evaporation (Ep) as E = K Ep, where K is the pan coefficient (K is typically in the range of 0.6 - 0.8).
** Required to calculate ML/km/year, assumes P above equals average annual wetted perimeter

These parameters are illustrated below:

Figure 1 – Channel cross section indicating parameter values to calculate the seepage rate
Figure 1 – Channel cross section indicating parameter values to calculate the seepage rate

Data to be collected Top button

Estimates of evaporation and rainfall can be obtained from the nearest weather station. However, more accurate results can be achieved using an evaporation pan and rainfall gauge adjacent to the pond.

As well as soil and hydraulic data for the channel, information about silt layers lining the channel is important in interpretation of results.

Site survey


The site should be surveyed before channel filling [while the channel is empty] to collect information on channel bed levels, channel cross-sections and structure or bank details. The survey should take account of the following requirements.
  • Full supply level (FSL) surveyed before pond construction works, so that the pond can be filled to this level during the test.
  • Reference pegs at each of the barriers, surveyed for location.
  • Hook gauges surveyed at the 0 or 1.0m mark on the gauges, with FSL and channel bed levels recorded at each gauge.
  • Survey to define the channel cross-section as accurately as possible at the pondage walls and approximately every 200m. The recommended number of points to be collected in each cross-section is presented in the table below. Each point in the cross-section is to be surveyed for elevation and chainage. The minimum number of points required also depends on the shape of the channel.
  • If a pondage test is repeated at a site after a year or more, the survey should be repeated in case there have been changes to the channel cross-section due to channel operation and maintenance.
Recommended number of survey points to be included in channel cross-section

Survey point
Reference

LHS Natural Surface ( 5m from toe of bank)

LNSO

LHS Natural surface at toe of bank

LNS

LHS Top of bank - outside

LTO

LHS Top of bank - inside

LTI

LHS Bed

LB

Centre Bed

C

RHS Bed

RB

RHS Top of bank - inside

RTI

RHS Top of bank - outside

RTO

RHS Natural surface at toe of bank

RNS

RHS Natural surface ( 5m from toe of bank)

RNSO

Survey definitions

Left-hand side (LHS) – Left-hand side based facing downstream
Right-hand side (RHS) – Right-hand side based facing downstream

Figure 2 –Survey points to be included in channel cross-section
Figure 2 –Survey points to be included in channel cross-section

Elevations should be surveyed to Australian Height data (AHD). It is beneficial to survey to Australian map grid (AMG) coordinates to allow consistency with other spatial techniques such as geophysics and groundwater bore locations for input to GIS mapping and analysis systems. A site plan showing all survey channel data (preferably an electronic version), should be prepared to help interpret pondage test data and other related information.

Pondage test soil barrier construction

Figures 3 and 4 - Pond barrier showing temporary plastic liner installation

Figures 3 and 4 - Pond barrier showing temporary plastic liner installation
Figures 3 and 4 - Pond barrier showing temporary plastic liner installation

Pond set-up and construction Top button

Individual ponds can be tested for a site-specific investigation. Multiple ponds may be used if data are required to extrapolate to other parts of the channel in conjunction with other data such as geophysical response for calibration. Barriers should be located so that individual ponds coincide with sections showing similar geophysical response. A minimum length of 50m is recommended. Back-to-back construction minimises the number of barriers required to be constructed.

Using an excavator and plastic or rubber membrane liner, barriers are compacted, lined and covered with soil to minimise or prevent seepage. An excavator will be required for construction of the banks. See figures 3 and 4 above showing two stages of a barrier under construction in a full channel.

Landowner permission to use soil adjacent to temporary bank locations saves on transportation. Holes are filled in when temporary barriers are dismantled after the tests. Soil used for barriers should have sufficient clay content.

Installation of monitoring gauges Top button

Hook gauges

Hook gauges are to be installed at both ends of each pondage section to eliminate potential wind effects. Gauges should be calibrated to millimetre accuracy. Data loggers can produce more accurate results and eliminate the need for gauge monitoring during the test.

Rainfall gauge and evaporation pan

Rainfall and evaporation must be measured to develop the water balance. A rainfall gauge and class A evaporation pan should installed in middle of the pond (or at the middle pondage for a series of ponds). More accurate evaporation rates are obtained if the evaporation pan is allowed to float in the pond. Specifications can be obtained from the Bureau of Meteorology.

Filling methodology

Pondage tests within each section should start as close as possible to simultaneously, with water levels at full supply level (FSL). To account for losses during the initial wetting period of the soil, the methodology should include one of the following:
  • Filling the pondages above FSL and commencing the test when the pondage level reaches the FSL.
  • Maintaining the pondage levels at FSL for half to one day before commencement of the test.
To obtain a consistent initial level across the ponds, barriers should be constructed within one day, and a pump used to transfer water from upstream into the ponds, and from pond to pond.

Set-up methods differ slightly vary depending on whether tests are being conducted at the start or end of the irrigation season.

Filling methodology at end of channel operation

The furthest downstream bank should be constructed first, working backwards towards the furthest upstream bank. The water level in the most downstream pondage should be allowed to back up to the highest degree, as this will experience the highest losses by the time the final pondage is constructed. A pump might be required to top up levels in the lower ponds before starting the test.

Filling methodology at beginning of channel operation

In dry conditions, the downstream bank can be fully constructed before the release of the water. The remaining barriers can also be constructed, taking advantage of the dry conditions.

To allow water to be transferred through the barriers, a suitably sized pipe should be installed towards the top of each bank, and each pipe adequately sealed when the filling of the ponds is completed. The use of these pipes will enable equilibrium to be maintained across all the ponds. A portable pump may be required to top up ponds.

Water being released to fill the ponds needs careful control. Once the test has commenced the flow coming down the channel needs to be virtually stopped. Overflow of the upstream bank cannot occur during the test. This makes the timing of the test crucial and operations personnel need to be prepared to shutdown the system for the test.

Checking of site for all possible inflows and outflows Top button

During and after filling of the ponds, an inspection should be carried out of all sealed structures and along both barriers of the test reach, to check for leakage and other signs of water loss (e.g. stock usage, pumps). If inflow or outflow sites are found, attempts should be made to measure or eliminate them.

Pondage test operation

Duration of test
  • The typical duration of a pondage test is in the range of four to ten days.
  • The duration of the test is best determined during the test and is dependent on the amount of measured seepage. Results should therefore be assessed daily during the test.
  • If rainfall during the test causes significant uncontrolled and unmeasured runoff into the pond, the test should be cancelled or extended as this inflow will not be accounted for accurately in the water balance.
Monitoring during the test
  • Data measurements (water-level gauges, pan evaporation and rainfall) should be taken daily, with at least two measurements taken on the first day of the test.
  • Accurate reading of hook gauges is usually only effective from inside the channel, which may require wading into the channel.
  • All water measurements should be recorded inside stilling wells to minimise short-term variations in the water level (e.g. due to wind-driven waves).
  • Gauges at the upstream and downstream end of each pondage should be read not more than 10 minutes apart.
  • Data should be recorded on a spreadsheet similar to that shown in Figure 2-5, which allows direct input for calculations.
Evaluation of test results Top button

The field-recorded data is used in the equations to determine the estimated seepage rate. Download the Microsoft Excel spreadsheets below for an example of, or to record your own pondage test calculation output.

Pondage Test Analysis Example: Pondage_example_Sep2003.xls (956Kb)
Pondage Test Analysis Blank: Pondage_blank_Sep2003.xls (956Kb)


Related pages

Top button

Pondage tests: summary
Pondage tests: applicability, practical implementation, experience from the trials, indicative costs

   

Home

How to use this website

Copyright

Disclaimer

Privacy

Page last reviewed on 25/6/04