IRRIGATION AUSTRALIA WEBSITE Channel Seepage Management Tool (Please click to return to home page)

About this website Contact us Site map

Home

Seepage risk, potential

Identification & measurement

General issues

Recom. approach &
techniques

Techniques

Inflow-outflow tests

Pondage tests

Point measurement

Soil & geological profile

Groundwater
assessment

Geophysical surveys

Remote sensing

Remediation

Remediation costs, benefits

Prioritisation of works

Project review

Case studies

Downloads

Glossary

References

Pondage tests: applicability, practical implementation, experience from the trials, indicative costs

On this page go to
Applicability
Practical implementation
Experience from the trials
Indicative costs
Related pages

Pages in this section include:

 

Pondage tests; summary

  Pondage tests: principle, method
Pondage tests: applicability, practical implementation, experience from the trials, indicative costs

This page provides a detailed description of the applicability, practical implementation, experience from the trials and indicative costs for the pondage tests channel seepage identification and measurement technique.

Applicability

Pondage tests are considered the standard for channel seepage quantification. The most accurate means of measuring channel seepage, they are suitable for benchmarking and assessing other methods.

Pondage tests can be undertaken at most locations to provide the channel seepage base data. At locations where there is hard rock, care must be taken to secure the barriers. In some very large channels, the cost of earth works may be prohibitive.

Inconvenience of conducting tests outside normal channel operation times and the cost of bank installation are factors to be considered for pondage tests. In the trials RWAs found it convenient to undertake tests at the end of the season.

The extent of pondage test work to be undertaken at a site depends on the objectives of the investigation.
  • If the investigation is aimed solely at determining the seepage rate along a specific length of channel, a single pond would be appropriate.
  • While a long section can be tested at minimal cost (i.e. only two barriers), if pondage tests are to be used to identify seepage within short-to-medium-length sections, multiple barriers will be required, which (especially for large channels) can be very expensive.
  • A minimum of four ponds is recommended for a section if results are to be correlated against geophysical data, point test data or groundwater analyses and used for extrapolation to larger lengths of channel.
Pondage tests are probably the most accurate post-implementation measurement technique. A difficulty may be obtaining a suitable seal between barriers and remediated sections.

Practical implementation Top button

Pondage tests must be conducted outside normal channel operation, and non-flow conditions introduce some inaccuracies. This means that:
  • The channel must remain out of use during tests.
  • Cost of barriers can be high, and sometimes prohibitive for very large channels.
  • Conditions do not reflect velocities and sediment loads carried during normal channel flow.
  • Pondage test results do not provide an indication of the spatial variation of losses within the reach isolated and only provide a bulk figure for seepage.
The best times for conducting pondage tests are at the end or beginning of the water distribution season, so as to minimise disruption to the system. Of these two options, the ideal time is at the end of the water distribution season, immediately before the shutdown of the system, as subsurface conditions are closest to those encountered during operation. Pondage tests conducted at the beginning of the season can be of advantage if initial channel start-up losses are of special interest.

Experience from the trials Top button

The set-up for the trials involved installation of six back-to-back pondage sections, each 150-300m long. Locations were determined based on inferred zones of high or low seepage. The results are an average of the seepage rate over the pond length and do not necessarily target areas with the highest seepage zones.

Trial results suggest that under full-scale investigation and operational programs, ponds could be located according to geophysical indicators of seepage. Where possible, barriers should be located so that they coincide with sections showing similar geophysical response. A minimum pond length of 100m is recommended.

Pondage tests were conducted successfully at a large number of sites in the trials. Six 150-300m long ponds were installed and monitored over a two-week period. A summary of the results is presented below.

Pondage test summary from the trials


Channel

Seepage rate range
(mm/d)

Average seepage rate
(mm/d)

Pondage section

Donald

9-48

35

6

Toolondo

1-11

7

6

Rocklands

4-13

8

6

Tabbita

6-10

7

6

Lake View

7-9

8

4

Dahwilly

4-16

10

6

Finley

4-7

4

6

Waranga Western

1-13

5

11


The sites tested were considered by RWAs to be high-seepage sites. The rates of seepage determined were variable along each channel. The range of rates along the channel sections appeared to be consistent with the geological profile at each site and the perceived significance of the seepage problem. However, there were anomalies identified in several locations.

Although pondage test seepage rates are the most accurate means of measuring channel seepage, they may still lead to an underestimation of seepage compared to channel flowing conditions. For example, at Dahwilly in SE NSW, where the geological profile is very sandy, it was expected that the rates of seepage would be high, although pondage test results from the selected sites suggested low rates of seepage. This is due to the effects of clogging caused by siltation when the water is stationary.

Indicative costs Top button

The most significant cost element for pondage tests is bank construction. Next is personnel time for monitoring during the tests. The cost estimates below assume that the RWA has the required equipment available for the tests, including hook gauges, rainfall gauge and evaporation pan.

Bank construction/removal:
  • Earthmoving contractor costs - These costs vary considerably depending on the availability of a suitable local clay source. Approximate costs for bank construction and removal in the IAL trials are listed below. These were for channels between 10-20m wide (at FSL) and 1.5-2m deep:
    • Wimmera Mallee Water: $1,000 per bank for seven barriers
    • Murray Irrigation: $715 per bank for 10 barriers
    • Murrumbidgee Irrigation: $780 per bank for seven barriers (including importing clay) and $560 per bank for five barriers (using on-site soil)

    Differences between authorities are attributable to different channel sizes, economies of scale for different number of barriers constructed and different charge-out rates for internal personnel.
  • Supervision by RWA personnel - Generally a least half a day would need to be allowed for supervision of bank construction.
  • Plastic lining - Plastic lining is recommended for barriers, and essential if the bank is not constructed with a suitable percentage of clay material. The cost of this for one pondage bank is relatively minor (e.g. $50-$100/bank). Additional personnel (two recommended) are required to lay this plastic. About one hour per bank should be allowed.
  • Cross-section and hook gauge surveying – A least one cross-section per 200m, or one at the upstream and downstream ends of the pond is recommended. Typical costs in this study for the cross-section surveying for six cells (every 200m) ranged from $600 (Murray Irrigation), $1,200 (Wimmera Mallee Water) to $2,000 (Murrumbidgee Irrigation). The variation is largely attributed to internal charge-out rate differences and use of external contractors.
  • Set-up costs – Activities including installing hook gauges, rainfall gauge and evaporation pan) can be conducted by RWA staff. This is likely to take half to one day.
  • Monitoring costs – Monitoring can be conducted by RWA staff. Costs depend on the number of cells at the site and bank spacing. Excluding travel time to the site, the daily time required on site for one cell is about 15 minutes. During trials the typical time required for monitoring six cells at one site was about half to one hour, including measurement of water levels, rainfall and evaporation. Monitoring should be conducted once per day for at least seven days.
Related pages Top button

Pondage tests: summary
Pondage tests: principle, method

   

Home

How to use this website

Copyright

Disclaimer

Privacy

Page last reviewed on 3/12/03