IRRIGATION AUSTRALIA WEBSITE Channel Seepage Management Tool (Please click to return to home page)

About this website Contact us Site map

Home

Seepage risk, potential

Identification & measurement

Remediation

Approach

Techniques

Earthen Lining
Hard surface lining
Flexible membrane
lining
Groundwater
intervention

Remediation costs, benefits

Prioritisation of works

Project review

Case studies

Downloads

Glossary

References

High-density polyethylene (0.75mm)

On this page go to
Description
Experience
Site preparation
Installation
Durability
Seepage reduction
Cost
Advantages and disadvantages
Related pages

Pages in this section include:

  Flexible membrane lining techniques
  Flexible membrane materials
  Covered liners
High-density polyethylene (0.75mm)
  Geosynthetic clay liners
  Exposed liners
  High-density polyethylene (2mm exposed)
  High-density polyethylene (1.5mm exposed)
  Linear low-density PE and very low-density PE
(1.5mm)
  DamSeal
  Unreinforced polypropylene (1mm)
  Unreinforced polypropylene (0.75mm)
  Reinforced polypropylene (1.1mm)
  Butyl rubber
  Asphalt

Description Top button

High-density polyethylene (HDPE), commonly used as a geomembrane, is similar to the material used in black polyethylene pipes. It has a broad chemical resistance and excellent UV resistance, but has a lack of flexibility and can develop brittle stress cracking at low stresses if not properly formulated.

Since HDPE is a very stiff material, it cannot be prefabricated into panels. Instead it is delivered to the site in rolls, usually up to 6m wide (9m widths are manufactured in the United States) and all the seaming is done on-site. The HDPE liner is rolled out and laid across the channel with overlapping pieces to enable weld joining.

Experience Top button

Studies in the United States have installed an HDPE plastic liner underneath a form of concrete cover (shotcrete, grout-filled mattresses and roller-compacted concrete) and have shown that this method has an effectiveness in reducing seepage in the order of 95% (Swihart and Haynes, 1999). However, in other studies an HDPE plastic liner underneath 400mm of earth cover was estimated to have an effectiveness of only 75% in reducing seepage (Sinclair Knight Merz, 1998).

The installation of covered HDPE (0.75mm) was trialed over a length of 1,200m in Wimmera Mallee Water’s Donald Main Channel.

Site preparation Top button

Channel reprofiling in the Donald channel Main Channel involved over-excavation by 400mm and regrading of batters to 1:3. Excavated material was stockpiled adjacent to the channel for use as backfill over the liner. Subgrade preparation involved removing all loose rubble from inside the channel and rolling the subgrade surface.

Installation Top button

Method of installation

The liner in this project was dragged across the channel with the assistance of a hydraulic powered unroller. Each length of HDPE was laid across the channel overlapping the previous piece by 100mm. Both sides of the liner were wiped clean of dust and moisture and then joined using wedge welding. The joint was tested for faults using a metal prong.

The liner was anchored into an anchor trench formed by a grader on the channel bank, and backfilled with 400mm of cover.

Figure 1 Unrolling the HDPE (0.75mm) liner into the channel profile
Figure 1 Unrolling the HDPE (0.75mm) liner into the channel profile


Figure 2 HDPE (0.75mm) - Welding the seams

Figure 2 HDPE (0.75mm) - Welding the seams


Following the testing of the joints, excavators placed 400mm of local soil over the liner. After a cover of 200mm had been placed the excavator gently compacted the fill using the excavator bucket. The backfill was stable on the 1:3 batter slope. Local soil was used as the channel experiences non-scouring velocities (generally less than 0.3m/s). Crushed rock scour protection was not required, significantly reducing installation costs.

Figure 3 Burying the HDPE (0.75mm) liner

Figure 3 Burying the HDPE (0.75mm) liner


At the downstream end of the trial section the HDPE liner was joined to an existing membrane, and the upstream end was trenched into the channel profile.

The site was fenced to prevent access to sheep and cattle, and signs identifying the liner’s location were installed.

Specialised equipment

A hydraulic unroller was used to assist the crews in placing the liner across the channel.

Installation issues
  • There were five noticeable bends in the 1,200m long channel, and from past experience it was estimated that an additional 4m of length of material would be required per bend. Additional length was quoted in the tender estimates to allow for these bends.
  • The use of the hydraulic unroller required access along the channel bank. The original placement of spoil from the channel bed did not allow for this, so the spoil had to be double-handled at certain locations.
  • Concern was raised over the quality of the thermal seams as dust, exacerbated by the wind, was fouling the liner prior to seaming. A dry clean cloth was used to clean the area. There was no testing of the seams apart from prodding with a metal prong. Future specifications for this type of installation should include non-destructive testing of the field seams and repair if necessary. This could easily be accomplished by air testing of double-wedge thermal seams or vacuum box testing.
  • Due to the wind direction the contractor shingled the downstream panel of HDPE over the upstream panel. To reduce the risk of water movement lifting the downstream panel and putting stress on the seam, specifications should stipulate that the upstream panel should be laid over the downstream panel.
Weather considerations

Installation times increase substantially in windy conditions as the material is more difficult to handle.
Welding cannot take place in wet conditions.

Durability Top button

It has been estimated that a well-installed buried HDPE liner has an estimated life of 25 years (Sinclair Knight Merz, 1998). However, some researchers have used a design life of 50 years for both buried and concrete-covered HDPE geomembranes.

The supplier advised that the 0.75mm HDPE material has a 10-year warranty.

Seepage reduction Top button

The baseline seepage rate at the Donald Main Channel ranged from 30-50L/m2/day. Post-remediation seepage assessments were undertaken in March 2003 and revealed a seepage reduction of between 87 and 92% (reduced to 3.8L/m2/day).

Cost Top button

A breakdown of the costs is presented in the table below. The total cost of $161,130 (2001), or $6.62/m2, is based on a supplied surface area of 24,346m2.

Table 1 Breakdown of costs for buried HDPE

Item

Cost ($)

Cost ($/m2)1

Site preparation (excavator, grader, etc.)

 $30,938.50

$1.27

Materials (inc. delivery)

$54,778.00

$2.25

Installation (contractor joining)

$22,566.18

$0.93

Backfilling (excavator, etc.)

$26,599.50

$1.09

WMW staff wages, on-costs, etc.

$12,154.30

$0.51

Fencing

$10,822.50

$9/m

Miscellaneous

$3,270.40

$0.13

TOTAL

$161,129.88

$6.62

1. Cost per square metre based on supplied material of 24,346m2.

The costs are indicative of costs faced for a commercial application in early 2001. These costs are exclusive of GST.

The price of HDPE (0.75mm) material increased to approximately $2.75/m2 in November 2001, which is more than the $2.25/m2 indicated by the costs incurred for this installation. Using this price, the total installation cost would have increased to approximately $7.10/m2.

Advantages and disadvantages Top button

Advantages
  • The HDPE liner can be bonded to concrete structures by dyna-bolting the liner using teflon strips as the interface between the concrete and the liner material.

Disadvantages

  • Subgrade preparation is critical, as the HDPE liner at 0.75mm is very susceptible to puncture. All protrusions, such as large clods, rocks or sharp objects must be removed from the substrate, and the backfill must also be free of this material.
  • Installation requires specialised skills and equipment to weld the seams.
Related pages Top button

Flexible membrane lining techniques
Flexible membrane materials
Covered liners
Geosynthetic clay liners
Exposed liners
High-density polyethylene (2mm exposed)
High-density polyethylene (1.5mm exposed)
Linear low-density PE and very low-density PE
(1.5mm)

DamSeal
Unreinforced polypropylene (1mm)
Unreinforced polypropylene (0.75mm)
Reinforced polypropylene (1.1mm)
Butyl rubber
Asphalt
   

Home

How to use this website

Copyright

Disclaimer

Privacy

Page last reviewed on 25/6/04